Additional Q&A #1 Q: Will the contractor be
required to have a performance and payment bond on the project in addition to the bid bond?
A:I don’t have an answer for that yet. I recommend including both as separate line items in your bid. If the Town Board requires them, they will already be factored in, and if they don’t
require either/both, then the listed amounts can be excluded from the contract award amount.
#2
Q: Is there a required bid/proposal form for the Boathouse Creek Park Bathroom RFP, or should contractors submit their own proposal format including the items listed in
Section 6? Also, is there a required bid bond form or may our surety provide their standard bid bond form?
A: There is not a specific bid/proposal form, nor a specific bid bond form. Contractors may submit their own form and sureties can provide
their standard bid bond form.